Construction of a small hydroelectric power station (HPP) with an installed capacity of 2.0 MW on the Akmolinsky main canal in Panfilovsky district of Zhetysu region
Construction of a small hydroelectric power station (HPP) with an installed capacity of 2.0 MW on the Akmolinsky main canal in Panfilovsky district of Zhetysu region
The project It provides for the construction of a small hydroelectric power station (HPP) with an installed capacity of 2.0 MW on the Akmolinsky main canal in the Panfilovsky district of the Zhetysu region. The maximum power generation capacity is 8,640,000 kWh.
- Indicator Results
- Investment amount, thousand US dollars 1 133
- NPV of the Project thousand, US dollars 460
- IRR, % 19
- EBITDA yield, %
- Payback period, years 14
- Discounted payback period, years - - 16